On 17 November, the Lao government signed a Project Development Agreement (PDA) with two developers for the proposed 1,275-megawatt (MW) Vilatsaphone Wind Power Project in Savannakhet Province.
Naseng-Wayo Renewable Resources Development & Investment Co., Ltd. and UPC Vietnam (Singapore) Pte. Ltd.
If completed, Vilatsaphone would become Laos’ largest wind farm. Its planned capacity is more than twice that of the 600-MW Monsoon project in southern Laos and greater than the 1,200-MW Nong project.
UPC Group Chief Executive Officer Andrew Sutherland said the project would supply clean, reliable electricity to the national grid, generate royalties and tax revenue over a 25-year concession, and create hundreds of skilled jobs.
During the 24-month PDA phase, the developers will analyze wind data, conduct geological surveys, and complete a feasibility study and basic design. They will also study grid connections and power sales. The findings, along with required approvals, will determine the project’s final offtake markets.
The project builds on earlier work in the province. In November 2023, the partners signed a memorandum of understanding (MoU) with the government to study a wind farm in Vilabouly, Atsaphone, and Phin districts. They also installed the province’s first meteorological mast in Phin to collect wind-speed data.
The plan includes a 500-kilovolt substation to transmit power to neighboring countries, particularly Vietnam.
Other Wind Projects in Savannakhet
The 48 turbines in the first phase of Savan 1, a 300-MW project, have operated commercially since late December 2025 and supply about 900 million kWh of electricity to Vietnam each year. Construction of the 195-MW second phase is scheduled to start at the end of this year, with operations expected to begin in 2027, Vietnamese media reported.
The two phases of Savan 1 will total 495 MW. T&T Group’s separate Savan 2 project has a planned capacity of 495 MW and an estimated investment of USD 768 million. The company is the primary investor, developer, and operator of the Savan projects. Savan 1’s first phase spans Phin and Nong districts, next to Vilabouly and Atsaphone.
T&T Group and Vinacom Investment and Trading Company exchanged an MoU for Savan 2 on 8 October. The companies plan to begin commercial operations by December 2028. Once Savan 1 and Savan 2 are complete, the projects together would provide nearly one gigawatt of wind power capacity.
Southern Laos Project Supplies Vietnam
The 600-MW Monsoon Wind Power Project, in Sekong and Attapeu provinces, began commercial operations in August 2025.
Billed as Southeast Asia’s largest onshore wind farm and Asia’s first cross-border renewable energy venture, the USD 950 million project uses 133 turbines to supply electricity to Vietnam Electricity (EVN).