Surveying, clearance, and destruction of unexploded ordnance (UXO) along the Laos-Vietnam Railway project in Khammouane Province has reached 90 percent completion, clearing the way for heavy machinery to begin construction, local media reported on 12 November.
The work is entering its final phase, with the project preparing to move into...
Construction of the Laos-China railway in Luang Namtha province has yet to commence as some UXO clearance activities need to be completed before the...